More capacity, Same precision. A Step forward for Lasered

Our next phase of development, the story so far.

Our new site on Crittall Drive

Growth rarely announces itself quietly. For us at Lasered Components, it arrived in the form of a second production site on Crittall Drive, right next door to our original Warner Drive factory in Braintree.

What followed was months of fit-out: new power, new flooring, new machines rolling in on the backs of lorries, and no shortage of site inductions. Then, on 18 May, the doors on Crittall Drive opened for production, taking our combined manufacturing footprint from 25,000 sq ft to 38,000 sq ft in one move.

It’s the single biggest physical expansion in our history, and it’s already changing how we work.

New laser

Why a second site?

Warner Drive has served us well since 1998, but growth needs room to breathe. Crittall Drive gives us a dedicated environment purely for stainless steel and non-ferrous materials, including aluminium, brass and copper.

Separating these materials from our mild steel production isn’t just about space. It means cleaner handling, better material segregation and less risk of cross-contamination, so the parts leaving Crittal Drive meet the same exacting standard customers expect from every Lasered Components job.

The Investment

Crittall Drive doesn’t stand alone. It’s one piece of a wider £6.5 million investment programme running through 2026, the largest we’ve committed to since the company was founded in 1998.

Across both sites, our laser fleet is growing from five machines to seven, all new TRUMPF systems, lifting our combined rated laser power by 57%, from 84kW to 132kW. Our press-brake facility has grown from two machines to five: a TruBend 5170, a TruBend 5130 and three TruBend 7050s, one of them paired with a TRUMPF Flex Cell that can load, bend and unload high-volume small parts for hours at a time. Later this year we’re bringing double-sided deburring and edge rounding in-house too, so more of the finishing work customers used to source elsewhere happens under one roof.

None of that capacity means much without a way to see it working. That’s where the Hub comes in, our own quoting, production and customer-tracking platform, built in-house and fully live since January 2026. It gives our estimators a live view of stock, capacity and workload when pricing a job, and gives customers a live link to watch their own order move from cutting through to delivery.

The results are already showing, and Crittall Drive is a big part of how we got there.

More volume, faster turnaround

None of this is capacity for its own sake. Since the Hub went live, lead-time accuracy on customer quotes has climbed, so the date we promise is the date we deliver.

Paired with the extra laser and press-brake capacity, the effect on volume has been significant. June 2026 was the busiest month in our history: 644,000 parts across 1,825 orders, output 15% above our previous monthly record & 40% higher than June 2025. Despite that surge, the average time from purchase order to delivery held at four working days, and rejection and rework volumes stayed broadly flat as a share of output.

In Karl’s words

“The availability of the neighbouring site gave us the opportunity to unlock a much larger growth plan for the company and for our team here in Braintree. This investment increases capacity, creates jobs and keeps us at the forefront of manufacturing technology.” — Karl Willett, Managing Director

What it means for you

More capacity. More consistent quality. A dedicated home for stainless and non-ferrous work, backed by the same fast turnaround and live order visibility across both sites. Whether it’s a one-off prototype or a high-volume run, Crittall Drive means we can take on more, without compromising on the standard you already rely on.

Crittall Drive Timeline Preview

The Crittall Drive Timeline

1 January 2026

We take possession

Crittal Drive building exterior Crittal Drive handover

Keys handed over on the 13,000 sq ft unit next door to Warner Drive.

Jan – April 2026

The fit-out begins

Fit-out at Crittal Drive Machine installation at Crittal Drive

New power, new flooring, and three new TRUMPF lasers arriving on site.

18 May 2026

Production goes live

First parts cut at Crittal Drive Production floor going live

Combined footprint grows from 25,000 sq ft to 38,000 sq ft.

Spring 2026

Three lasers, fully running

TRUMPF TruLaser 5030 in operation TRUMPF laser cutting stainless steel

Two 12kW and one 24kW TruLaser 5030, dedicated to stainless and non-ferrous work.

June 2026

Our busiest month on record

Production floor at Crittal Drive Finished parts at Crittal Drive

644,000 parts across 1,825 orders, still delivered in an average of four working days.